Henkel

Expansion production facility for adhesives
Kornye, Hungary

The adhesives unit has a long term development. The first phase was to expand its production capacity of hot melt manufacturing with a new plant. Henkel selected Bilfinger Tebodin as experienced international company with whom they could build a long term relationship working on various locations. 

Bilfinger Tebodin started with tender document preparation and tender process support. The services were expanded to process design of the hot melt technology and both Health, Safety and Environment (HSE) and technical supervision for the construction phase of the plant.

A team of consultants and engineers worked with Henkel on combining the large number of different products to be manufactured with the demand for a high production capacity. From beginning to end, we have been focusing on the project as a best practice for Henkel’s standards and expectations.